$2,235,000
Project Budget
Brixen & Christopher Architects
Project Architect
30,000 SF
Project Size
CM/GC
Procurement
April 2010 To February 2011
Duration
TerraTek
Owner
OVERVIEW
The TerraTek lab expansion and building remodel project in Salt Lake City involved a build-out and renovation of an existing tilt-up concrete building. The project added a steel structure, including a second floor for a total build-out area of 21,100 SF. To improve functionality and aesthetics, 9,000 SF of existing space was remodeled.
The new build-out included conference rooms, offices, open office spaces, restrooms, and a 4,400 SF high-bay manufacturing area equipped with a 5-ton crane. It also featured advanced laboratory space with four fume hoods to support TerraTek’s specialized operations. The remodeled areas included a new front lobby providing a secure entrance, a “Town Hall” meeting space, additional offices, laboratory space, a café, and additional restrooms.
The existing building remained occupied throughout the construction process. The Gramoll team carefully scheduled and phased construction to minimize disruption to TerraTek’s ongoing operations.
SIMILAR PROJECTS
U of U BPRB Lab Remodel Level 2
EVR ASPIRE, Utah State University
Sensapure Tenant Improvement
The Nora Eccles Harrison CVRTI, University of Utah
HPER East Build Out Remodel
New Welding Center, Uintah Basin Technical College
Tooele Science and Technology Building, Utah State University
TerraTek Lab Expansion & Building Remodel
USTAR BioInnovations Center Utah State University
Bingham Entrepreneurship and Energy Research Center, Utah State University
DATC Barlow Technology Building
Fredrick Sutton Geology University of Utah
Sant Engineering Innovation, Utah State University